In the Plan Risk Responses process, an accept strategy for a negative risk or threat indicates that the project team has decided:________. 
A. To agree with the project manager. 
B. To eliminate a specific risk or threat, to reduce the probability and / or impact of an adverse risk event to be within acceptable threshold limits, or to pursue an opportunity actively. 
C. Not to change the project management plan to deal with a risk, or it is unable to identify any other suitable response strategy. 
D. To purchase insurance, or to require performance bonds, warranties, and guarantees.